Issue - decisions

Decision to approve the expenditure of up to £512,774 for the capital works at Aylestone School, Herefordshire.

27/06/2024 - Decision to approve the expenditure of up to £512,774 for the capital works at Aylestone School, Herefordshire.

The current schools capital maintenance programme to include the emergency works of concrete panel works at the C Block at Aylestone School in the current programme as urgent works.

Herefordshire Council to award a contract to supplier S C Joseph Ltd who
was appointed by the school and already started works on site for the capital works required at the C Block at Aylestone School Herefordshire.

Approve the expenditure of up to £455,799.13 for the works, which includes a contingency of up to £21,701.33

Approve the expenditure of up to £56,975 for internal and external professional fees.

Responsibility for monitoring the programme to be carried out by the Capital Senior Project Manager within the spend budget.