Issue - decisions

Upgrade and Renewal of CCTV Equipment

15/04/2019 - Upgrade and Renewal of CCTV Equipment

That:

(a)       approval is given to implement the CCTV infrastructure upgrade and renewal as identified in the report MSC Herefordshire Report V1.4 at a capital cost of not more than £184k;

(b)       Global MSC be commissioned to write a specification and project manage the upgrade and renewal of equipment as identified in the report MSC Herefordshire Report V1.4 at a cost of £6,246; and

(c)       the acting assistant director for technical services be authorised to take all operational decisions, including award of contract, to implement the above recommendations.