Highways Maintenance Challenge Fund - Timescale and Methods for Completion of Phase 2
04/05/2018 - Highways Maintenance Challenge Fund - Timescale and Methods for Completion of Phase 2
That:
(a) the works that are required to complete the Local Highway Maintenance Challenge Fund project be completed in two short windows separated by approximately a year. Each to be as short as period as practically possible using a combination of daytime and overnight road closures and/or 7 day working; and
(b) the budget for these works be increased by £0.5m to £8.5m, this increase to be accommodated by directing up to £0.5m of expenditure toward these works from the £4.6m that has been approved for highway maintenance in the 2018/19 capital programme.