ENTERPRISE ZONE CAPITAL INTERVENTIONS PHASE 4

15/06/2018 - ENTERPRISE ZONE CAPITAL INTERVENTIONS PHASE 4

That:

(a)       £2.55m from the enterprise zone capital programme provision be allocated to the following infrastructure interventions at the Hereford enterprise zone:

Augment the zone-wide ground raising solution utilising spoil from the North Magazine

£450k

Road access interventions

£400k

Utilities investment as follows:

  • Water, foul, gas main provisions to the North Magazine
  • Utilities for plot C1
  • Specific plot by plot provision as required

 

£750k

£300k

£150k

Plot works

£300k

Site wide improvement works including strategic signage and landscaping interventions

£200k

Total

£2.55m

(b)  the Economic Development Manager be authorised to take all necessary operational decisions to implement the above interventions, including the appointment of contractors following an appropriate procurement process.