DCSE2007/1478/F - LAND ADJACENT TO 'MARSH COTTAGE' PONTSHILL, ROSS-ON-WYE, HEREFORDSHIRE, HR9 5SZ. (AGENDA ITEM 17)

Erection of one dwelling.

Minutes:

Erection of one dwelling.

 

The Principal Planning Officer reported the following:

 

  • Environment Agency note that part of the site is located within flood zone 3.  However the proposed dwelling and sewage treatment plant is located outside of this high risk area.  It is also noted that there is a buffer strip of 7 metres from top of bank of watercourse.  There should be no increase in ground levels above existing in the 1% floodplain to prevent flood risk to the proposed dwelling and land elsewhere.  On the basis of the above we would raise no objection to the proposed dwelling subject to imposition of conditions.
  • One letter has been received from the owner of the application site in support of the application.
  • Weston under Penyard Parish Council objects to the proposed modification to the design, i.e. additional windows in roof.  Original plan should be maintained.

 

In accordance with the criteria for public speaking Mr. Smith, the applicant’s agent, spoke in support of the application.

 

RESOLVED

 

That subject to no further objections raising additional material planning considerations by the end of the consultation period, the officers named in the Scheme of Delegation to Officers be authorised to approve the application subject to the following conditions and any further conditions considered necessary by officers:

 

 

1       A01 (Time limit for commencement (full permission))

 

         Reason: Required to be imposed by Section 91 of the Town and Country Planning Act 1990.

 

2       B01 (Samples of external materials)

 

         Reason: To ensure that the materials harmonise with the surroundings.

 

3       F48 (Details of slab levels)

 

         Reason: In order to define the permission and ensure that the development is of a scale and height appropriate to the site.

 

4       The foul drainage from the proposed development shall be discharged to a treatment plant which meets the requirements of British Standard BS 6297: 1983, and which is provided in accordance with the details submitted dated July 2006 (including drawing no. 584:01/02A) unless otherwise agreed in writing by the local planning authority.

 

         Reason:  To provide a satisfactory method of foul drainage and prevent pollution of the water environment.

 

5       Any facilities for the storage of oils, fuels or chemicals shall be sited on impervious bases and surrounded by impervious bund walls.  The volume of the bunded compound shall be at least equivalent to the capacity of the tank plus 10%.  If there is multiple tankage, the compound shall be at least equivalent to the capacity of the largest tank, vessel or the combined capacity of interconnected tanks or vessels plus 10%.  All filling points, associated pipework, vents, gauges and sight glasses must be located within the bund or have separate secondary containment.  The drainage system of the bund shall be sealed with no discharge to any watercouse, land or underground strata.  Associated pipework shall be located above ground and protected from accidental damage.  All filling points and tank/vessels overflow pipe outlets shall be detailed to discharge downwards into the bund.

 

         Reason:  To prevent pollution of the water environment.

 

6       D03 (Site observation - archaeology)

 

         Reason: To allow the potential archaeological interest of the site to be investigated and recorded.

 

7       G04 (Landscaping scheme (general))

 

         Reason: In order to protect the visual amenities of the area.

 

8       G05 (Implementation of landscaping scheme (general))

 

         Reason:  In order to protect the visual amenities of the area.

 

9       G01 (Details of boundary treatments)

 

         Reason: In the interests of visual amenity and to ensure dwellings have satisfactory privacy.

 

10     E16 (Removal of permitted development rights)

 

         Reason:  To protect the amenities of neighbours.

 

11     F18 (Scheme of foul drainage disposal)

 

         Reason: In order to ensure that satisfactory drainage arrangements are provided.

 

12     H03 (Visibility splays)

 

         Reason: In the interests of highway safety.

 

13     H05 (Access gates)

 

         Reason: In the interests of highway safety.

 

14     H09 (Driveway gradient)

 

         Reason: In the interests of highway safety.

 

15     H12 (Parking and turning - single house)

 

         Reason: In the interests of highway safety and to ensure the free flow of traffic using the adjoining highway.

 

16     E19 (Obscure glazing to windows)

 

         Reason: In order to protect the residential amenity of adjacent properties.

 

17     E18 (No new windows in specified elevation)

 

         Reason: In order to protect the residential amenity of adjacent properties.

 

Informative(s):

 

1       HN01 - Mud on highway

 

2       HN05 - Works within the highway

 

3       HN10 - No drainage to discharge to highway

 

4       HN22 - Works adjoining highway

 

5       N19 - Avoidance of doubt

 

6       N15 - Reason(s) for the Grant of Planning Permission

 

7       ND03 – Contact Address

Supporting documents: