The head of internal audit presented the progress report on the 2018/19 internal audit plan was presented.  

 

The head of internal audit reported that a meeting with the chief finance officer had taken place to discuss the timing of the internal audit of the South Wye Transport Package.      The audit would be undertaken in quarter 1 of the 2019/20 internal audit plan.   

 

Following a query from a member of the committee, it was confirmed that SWAP would be looking at the Southern Link Road capital programme as part of the review of the Blue School House recommendations which was due to be reported to the March 2019 committee meeting.   This would check whether the recommendations from Blue School House were being implemented in other capital projects. 

 

The head of internal audit reported that since the last progress report to the committee:

 

·                16 audits had been completed

·                2 were in draft

·                11 audits were in progress

·                There were 2 audits with partial assurance which were SEN transport and Health and Safety. 

·                No significant high corporate risk had been identified. 

·                There had been 2 additions to the audit plan which were honorarium, market forces and standby and on call allowances and treasury management.   

·                The mandatory training audit had been moved to 2019/20.

·                The local population forecast using for future planning such as house building requirement had been removed from the audit plan

 

In response to queries raised by members of the committee in connection with the health and safety audit, the head of HR and organisational development confirmed the following:

 

·                There are a low number of accidents reported but it was believed there was under reporting so action was being taken to raise the profile of this area.

·                A new health and safety manager would be starting at the beginning of February. 

·                Risk assessments in high risk areas are completed and are done well. 

·                That the display screen equipment (DSE) assessment was covered as part of the induction and mandatory training.    It was noted that it was the responsibility of the employee.  

·                There are no health and safety champions but that this was a good idea so it would be looked into. 

·                There were processes in place to ensure that staff have the security required to work safely.

 

Following a request from a member of the committee, it was confirmed that internal audit would be starting work in February to look at the processes used by the children’s and families directorate following the two recent high court cases.

 

The head of internal audit confirmed that data quality is normally good and that SWAP are always provided with the data requested.   When checking a key performance indicator (KPI), the methodology used for the calculation is requested and if SWAP cannot resolve the calculation, then they will make a recommendation to the service. 

 

With regard to the treasury management internal audit which had been added to the audit plan, it was confirmed that in comparison to other councils, Herefordshire is doing well.  

 

In response  ...  view the full minutes text for item 346