Decision details
Gas Installation to Plot C1A and C1B
Decision Maker: Corporate Director – Economy & Environment
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
The installation of gas to Plot C1A and C1B
forms an essential part of preparing the land for sale and
development.
Total Utility Connections Limited have been identified as the
preferred supplier to carry out the work. Four organisations were
invited to quote for the work using the Council ITQ template forms.
Three responses were received of which Total Utility Connections
Limited scored highest (against combined cost and quality).
Contact: Neil Taylor, Interim director of economy and place Email: Neil.Taylor@herefordshire.gov.uk Tel: 01432 260921.
Publication date: 04/02/2022
Date of decision: 04/02/2022