Decision details

Hereford Transport Package

Decision Maker: Cabinet member infrastructure

Decision status: Implemented

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

 

To confirm the 2019/2020 programme of work within the approved funding allocation and spending the additional grant of £150k received in 2018/19.

On 15 February 2019 Council approved the revised capital programme. This included provision of £3.5m in 2019/2020 for the Hereford Transport Package. This report recommends approval to spend this budget in accordance with the feasibility case which supported the Hereford Transport Package capital bid and is contained in Appendix 1 of this report.

Decision:

That:

(a)          the Director for Economy and Place is authorised to take all necessary steps to progress detailed design and consultation including commissioning external professional advisors to inform future decisions on the Hereford Transport Package to a maximum further cost of £3.65m to deliver:

Completion of detailed design of the bypass to a standard for a planning application in accordance with an agreed costed programme.

Alternative options considered:

1.         An option for proceeding with Hereford growth proposals (Local Plan Core Strategy) without the provision of a bypass was considered and discounted during the Core Strategy process. Not progressing this work will mean the HTP objectives and core strategy growth targets cannot be achieved.

 

Reason Key: Expenditure and strategic nature / impact on communities;

Wards Affected: Belmont Rural; Credenhill; Holmer; Kings Acre; Queenswood; Stoney Street; Whitecross; Wormside;

Contact: Mairead Lane, Acting Assistant Director for Highways and Transport / Head of Infrastructure Delivery Email: mlane@herefordshire.gov.uk Tel: 01432 260944.

Publication date: 11/03/2019

Date of decision: 11/03/2019

Effective from: 16/03/2019