Change to BT Contracts for Fastershire Broadband Strategy Stage 3 Lots 3a and 3b
Decision Maker: Assistant director Corporate Support (Historic)
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Decision:
That a change to the Lot 3a and 3b contracts
is approved by the authorities with the effect of:
a. Increasing the subsidy for Lot 3a by £72k
b. Decreasing the subsidy for Lot 3b by £14k
c. Decreasing the number of premises to be reached by the Lot 3a
contract by 800 premises
d. Increasing the number of premises to be reached by the Lot 3b
Contract by 5 premises.
Contact: Natalia Silver, Service Director - Corporate Services Email: nsilver@herefordshire.gov.uk Tel: 01432260732.