Decision details
Variation to public realm annual plan 2018/19
Decision Maker: Assistant director environment and place (Historic)
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Decision:
To vary the public realm annual plan
2018/19;
1) Holme Lacy Road Cycle Route: to extend the programme for Holme
Lacy Road cycle route and reprofile the project budget to
£75,000 (reduction from £325,000);
2) Re-allocation of budget; to allocate the £250,000 budget
(above underspend) to the resurfacing programme for 2018/19
Contact: Laura Lloyd, Commercial and contract manager Email: Laura.Lloyd@herefordshire.gov.uk Tel: 07792 880055.
Publication date: 30/07/2018
Date of decision: 27/07/2018