Decision details

CUSTOMER SERVICES AND LIBRARIES

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

The purpose of this report is to outline options for Customer Services and Libraries in the light of continued budget pressures and for Cabinet to consider future delivery of centres and services for implementation in 2015/16.

Decision:

THAT:

 

(a)       authority be delegated to the Director for Economy, Communities and Corporate, in consultation with the Cabinet Members for Corporate Services and Contracts and Assets, to implement changes to service delivery (points 17-26) in order to release savings for April 2015;

 

(b)       consideration be given to closing the customer services centre at Franklin House and offering a combined customer and library service at the Broad Street site; and

 

(c)       should the decision taken in respect of recommendation (b) above be to progress a combined customer and library service at the Broad Street site, the cost of modernising the premises be financed through capital receipts from the disposal of selected operational properties to avoid extending the council’s borrowing requirements

 

Reasons for the decision:

1          The report and corresponding recommendations aim to balance the requirement for savings, with delivery of a countywide library and customer services presence based on contemporary way of accessing services.  The proposals also reflect the drive towards greater community involvement and management of services.

 

2          The outline budget saving for customer services and libraries within the budget consultation was £700,000.  A proportion of these savings have already been met through the redesign of service implemented as a result of the Cabinet decision on the 19th September 2013.  Therefore the recommendation is based on achieving an additional £423,978 (rounded up to £424,000) from customer services (which includes the running front facing library service and contact by phone).

 

Alternative options considered:

1              Earlier release of budget savings –recommendation (a) is founded on realising the savings from April 2015 based on the findings of the Impact and Needs Assessment (Appendix 1) to allow for service transformation, establishment of community partnerships and wider cultural change in how services are accessed.  The alternative is to achieve the savings earlier through the immediate withdrawal services, with the consequent community impacts.

 

2              Retain current operation – this option would retain the overall current model of service based on the revised opening hours (as of 3rd February 2013).  However, a reduced level of savings would be achieved (approx. £100,000) based on the bringing together of operations in Ledbury, reconfiguration of the Bromyard Centre, and efficiencies regarding redesign of face to face and phone contact, requiring commensurate savings to be made in other service budgets.

 

Reason Key: Expenditure and strategic nature / impact on communities;

Wards Affected: (All Wards);

Publication date: 23/01/2014

Date of decision: 23/01/2014

Effective from: 29/01/2014