Decision to contract Velta Construction Ltd to deliver the Lugwardine Traffic Calming Scheme.
Decision Maker: Corporate Director – Economy & Environment
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Decision:
To award a contract to Velta Construction Ltd
– to the value of £398,791.59 for the designed
Lugwardine Traffic Calming Scheme.
To build in a 10% contingency amount bringing the total allocated
to: £438,670.74
To further delegate all operational and budgetary decisions up to
the maximum value of £438,670.74 for this scheme to the
Interim Delivery Director Infrastructure, Capital Programme Manager
and Capital Project Manager.