Plot C1 Cycleway
Decision Maker: Director of Economy and Place (Historic)
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
To award contract to Walsh Construction
Limited to deliver the construction phase of the missing link in
the cycleway across the Hereford Enterprise Zone around Plot C1.
Work will take place along the northern edge of the Straight Mile
and up into Chapel Road. The quoted cost for delivery of the works
is £258,925.96. An additional £25,892.60 contingency
needs to be included based on the risk analysis carried out by
Summers Inman LLP, who will project manage the new development on
behalf of the council. The total amount required to implement this
decision is therefore £284,818.56.
Contact: Neil Batt, Enterprise Zone Capital Programme Manager Email: Neil.Batt@herefordshire.gov.uk Tel: 01432 383694.
Publication date: 01/09/2021
Date of decision: 01/09/2021