Decision details

Approval of Main Contract budget and Furniture Fixtures and Equipment budget to finance the fit out of the Shell Store – January 2021

Decision Maker: Director of Economy and Place (Historic)

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

The Shell Store incubation centre project has materially completed construction, the building was handed over to the council in September 2020. There are currently a number of snagging and small scale works being undertaken on the building by the main contractor, Barnwood.

Barnwood and Mace, as the council’s appointed project manager, are liaising in relation to these snagging and small scale works.

In August 2020 a decision was taken to approve budget expenditure against a number of items including the allocation of £50,000 from the Fixtures, Fittings and Equipment budget towards the procurement of items to fit out the Shell Store café and reception areas. The works to the café and reception are now materially completed.

There is a need to undertake the fit out and installation of a number of other items within the building that will be material to its operation and marketability.

These works include relatively significant expenditure on telecommunications equipment alongside several, more minor work requirements.

The telecommunication works requires the installation of communication equipment and wifi to serve all the separate offices and the associated support facilities – meeting rooms and reception. New communication equipment is required to make the links from the fibre input to the Shell Store comms room and all the individual rooms. This will enable each tenant to have their own secure connection and their data usage can be monitored and charged for.

Additional work is required on the wifi network to ensure that it is available throughout the building and that occupants can move from office to atrium and other spaces with the same connectivity and security. The cost for undertaking this work is estimated by ITS, the Enterprise Zone communications contractors, to be: £135,000.

This work is considered essential for the building to be able to attract the high quality businesses that form the target occupants. Given the specialist technical requirements required to install the wifi network the work is outside the specification of the main contract budget. Inclusion of high quality communications within the building was a consideration within the business case and the project budget of £7.315m. This work will not lead to an extension of the existing project budget and can be managed within existing budget lines as demonstrated in the finance section below. The Programme Board recommended that a detailed and separate procurement exercise is completed to commission this work and a delegated budget of £135,000 is set aside for this purpose.

In addition to this relatively significant expenditure Mace have advised that a certain amount of fit out of the atrium and public areas of the building will be required, this has been confirmed with operators of similar facilities. There is a collective need to purchase items such as, but not limited too, security lockers for users, TV’s for use in the reception heritage pod, and public areas, furniture to facilitate ad hoc meeting space within the atrium, furniture to equip meeting spaces, furniture for the conference facility etc. An appropriate procurement exercise will be undertaken to purchase each of these, and any other, required items.

Individually many of these items will be at a relatively low value and requiring individual budget approvals for each is not considered an appropriate use of officer resource. It is recommended that £50,000 from the Shell Store fixtures, fittings and equipment budget is delegated to the Project Manager in consultation with the spend manager against the above listed items, and any others that the Project Manager and Project Lead considers appropriate.

The building has the infrastructure to accommodate up to four electric vehicles charging points, the charging points themselves are not yet installed and were outside the scope of the construction commission. The installation of the charging points will assist in the achievement of BREEAM points which determines the overall BREEAM rating of the building. Estimated cost for the installation of two chargers providing four charging points is no more than £10,000. The Programme Board recommend that a suitable procurement exercise is undertaken to install the charging points and that a budget of £10,000 is set aside for this purpose from the Fixtures Fittings and Equipment Budget.

Approval of expenditure against budget will based on recommendations from the Shell Store Project Manager/Project Lead, and where appropriate consultation with the Programme Board.


Contact: Nick Webster, Economic development manager Email: nwebster@herefordshire.gov.uk Tel: 01432 260601.

Publication date: 27/01/2021

Date of decision: 27/01/2021

Accompanying Documents: