Decision details
Pothole & Challenge Fund.- Programme of works Footways and Cycleways – PROW
Decision Maker: Acting Assistant Director for Highways and Transport
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
On 17 September 2020 the Director for Economy
and Place under the delegation from the Council of 6 August 2020
confirmed the addition of £7.674m pothole and challenge fund
works to he delivered through the public realm annual plan
2020/2021 as follows:
Carriageway Works
£ 2,604,000
Structures and Stability
£ 3,160,000
Footways & Cycleway
£ 400,000
Countywide Drainage Improvements
£ 760,000
Signal, Roadmaking,
£ 750,000
Signs & Safety Barriers
Total
£ 7,674,000
That record of officer decision can be seen on the councils
website by following the link below:
http://councillors.herefordshire.gov.uk/ieDecisionDetails.aspx?ID=7181
The Footways and Cycleways element included budget of £114K
for use on PROW Market towns as set out below.
This Rood confirms this programme for this element of works as
listed in Appendix A
Contact: John Manterfield, Commercial and Contract Manager Email: John.Manterfield@herefordshire.gov.uk.
Publication date: 26/01/2021
Date of decision: 26/01/2021