Decision details
Public Realm annual plan programmes of work
Decision Maker: Acting Assistant Director for Highways and Transport
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
Additional investment into the Public Realm
was provided through the pothole and challenge fund, this allocated
£7.674M of funding, some of which was initially earmarked to
deliver the following project in year. This funding must be spent
by 31 March 2021.
An initial programme of works on which this funding would be spent
was developed and set out in a record of officer decision dated 17
September 2020 and this set out the programme of projects as
follows:
U65606 Paunton Rock Armour £200,000
C1011 Kinsham deck replacement Phase2 £600,000
C1001 Buckton deck replacement Phase2 £600,000
repairs to C1072 Kington Bridge Phase 2 £200,000
A4113 Leintwardine £150,000
This report can be seen on the councils website by following the
link below:
http://councillors.herefordshire.gov.uk/ieDecisionDetails.aspx?ID=7181
Similarly additional Highway asset management (HAM) funding was
provided and funded the following programmes of work :-
Marshfield construction works - £120,000
Kington concrete repairs (split funding with above)
£200,000
However constraints have subsequently been imposed by the
Environment Agency on the ability to enter the water course to
undertake these projects to the anticipated programme which means
for these projects the earliest start date on site is now May 2021.
The following major schemes are affected:-
• Paunton Rock Armour - EA constraints on in river working,
unable to get into the river before May 21 at the earliest Kinsham
Deck Replacement - EA constraints 15th June earliest in river work
-
• Buckton Deck Replacement - EA constraints 31st May earliest
in river work
• Kington Bridge Concrete Repairs. EA restrictions on placing
scaffolding under bridge. May earliest lifting of
restrictions
• Marshfield bridge construction
Whilst design work and procurement of prefabricated elements of the
projects will be undertaken in 2020/2021 construction work cannot
commence until 2021/2022 as a result of the constraints above. This
results in a forecast anticipated underspend in 2020/20211 of
£1.641M on those elements affected by entry into the water
courses with respect to the pothole and challenge budget, and for
the same reason £245K with respect to the HAM funding
In order to deliver the intended agreed programme of projects set
out above the schemes will now be delivered from the councils
Investment in C & U roads capital budget next financial year,
and the C and U roads work that was to be delivered from that
budget will be undertaken this financial year funded from the
pothole and challenge fund grant money.
These works can be funded from that highway maintenance grant
funding.
The HAM funding of £245K is to be carried forward into
2021/2022 to align with the new programme requirements
Contact: John Manterfield, Commercial and Contract Manager Email: John.Manterfield@herefordshire.gov.uk.
Publication date: 26/01/2021
Date of decision: 26/01/2021