Decision details

£2m Investment in the C and U road network - confirmation of the delivery programme

Decision Maker: Cabinet member Infrastructure and transport

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

 

To approve the £2m investment in C and U roads and the £2m investment in infrastructure assets was made on 6 August 2020, as set out in the decision for the Capital Investment in Infrastructure 2020/21 Public Realm Annual Plan

 

The report recommendation required confirmation that the programme has been developed following the survey of the network, this report confirms the survey has been completed and that the delivery programme is prepared for delivery.

 

Decision:

That:

The £2m investment in the C and U road network is programmed for delivery following the survey of the network and assessment of the data, to approve and deliver the works through the Public Realm Contract from January through to March 2021.

Alternative options considered:

 

1.         Not to deliver, but this is not recommended as the condition of the network is in need of investment and this option would be contrary to the council resolution made at the meeting on  14 February 2020.

 

Reason Key: Expenditure;

Wards Affected: (All Wards);

Contact: Bruce Evans, Engineering Manager Email: bje@herefordshire.gov.uk Tel: 07792880548.

Publication date: 14/01/2021

Date of decision: 14/01/2021

Effective from: 21/01/2021

Accompanying Documents: