Decision to deliver improvement works at Leominster MAO

Decision Maker: Director of Economy and Place (Historic)

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

Following the decision to deliver the improvement works at Leominster MAO the BWOW programme Board requested and approved a revised layout for the building which increased the scheme cost by £30k and extended the programme by two weeks.

Contact: Chris Jenner, Assistant director for technical services Email: cjenner@herefordshire.gov.uk Tel: 01432 261941.

Publication date: 19/06/2020

Date of decision: 19/06/2020