Issue details
Record of Officer Decision - Procurement of Priority Flood Repair Works
That:
• All remaining elements of the Fownhope work (estimated
scheme value £1m including all management support) be
delivered through the Public Realm Services Contract;
• The Witney of Wye instability (estimated scheme value
£0.5m including all management support) be delivered as a
design and build commission;
• The Various flood damage Sites (estimated scheme value
£0.962m including all management support) be delivered
through a new framework contract aimed at providing a
‘post’ COVID opportunity directly to local SMEs;
and
• The Managing Agent support to the council’s own
project and contract management costs, as required to deliver these
schemes, is commissioned through the Public Realm Services
Contract.
Decision type: Non-key
Decision status: Recommendations Approved
Notice of proposed decision first published: 23/09/2020
Decision due: 22 September 2020 by Director of Economy and Place (Historic)
Contact: Mairead Lane, Acting Assistant Director for Highways and Transport / Head of Infrastructure Delivery Email: mlane@herefordshire.gov.uk Tel: 01432 260944.
Decisions