Issue details

Shell Store incubation centre project revision

To seek approval for the revised finances and business case for the  "Shell Store" project: an extensive refurbishment and conversion of the redundant Shell Store building within the Hereford enterprise zone, to create a business incubation and research facility that will support business growth and job creation. Additional approval to let a contract for the construction of the centre is also sought.

The key revisions to the project include:

"           To increase the project budget by £818,000 to a total of £7.316m;

"           The increased budget reflects the high construction inflation experienced since the previous approval and an increase in the contingency to a more appropriate sum;

"           The project has been delayed due to the time required to secure the external funding package, specifically securing ERDF and LEP funding.

Decision type: Key

Reason Key: Expenditure;

Decision status: Recommendations Approved

Wards affected: Dinedor Hill;

Notice of proposed decision first published: 03/07/2018

This decision will be taken under urgency procedures.

Reason for urgency:
To avoid delay in the project implementation programme which could put at risk external funding secured for the project if the programme timeline is not increase.

Decision due: 27 July 2018 by Cabinet member contracts and assets

Lead member: Cabinet member contracts and assets

Lead director: Director for economy, communities and corporate (Historic)

Department: Economy, communities and corporate (Historic)

Contact: Gavin Stephens, Economic development officer Email: Gavin.Stephens@herefordshire.gov.uk Tel: 01432 260177.