Shell Store incubation centre project revision
To seek approval for the revised finances and business case for the "Shell Store" project: an extensive refurbishment and conversion of the redundant Shell Store building within the Hereford enterprise zone, to create a business incubation and research facility that will support business growth and job creation. Additional approval to let a contract for the construction of the centre is also sought.
The key revisions to the project include:
" To increase the project budget by £818,000 to a total of £7.316m;
" The increased budget reflects the high construction inflation experienced since the previous approval and an increase in the contingency to a more appropriate sum;
" The project has been delayed due to the time required to secure the external funding package, specifically securing ERDF and LEP funding.
Decision type: Key
Reason Key: Expenditure;
Decision status: Recommendations Approved
Wards affected: Dinedor Hill;
Notice of proposed decision first published: 03/07/2018
This decision will be taken under urgency procedures.
Reason for urgency:
To avoid delay in the project implementation programme which could put at risk external funding secured for the project if the programme timeline is not increase.
Decision due: 27 July 2018 by Cabinet member contracts and assets
Lead member: Cabinet member contracts and assets
Lead director: Director for economy, communities and corporate (Historic)
Department: Economy, communities and corporate (Historic)
Contact: Gavin Stephens, Economic development officer Email: Gavin.Stephens@herefordshire.gov.uk Tel: 01432 260177.
Consultees
Local member
Details of any declarations of interest: n/a
Decisions
- 27/07/2018 - Shell Store incubation centre project revision
Documents
PDF 210 KB