Decision details

Gas Installation to Plot N4a

Decision Maker: Director of Economy and Place (Historic)

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

The installation of gas to Plot N4a forms an essential part of preparing the land for sale and development.

TUC Limited have been identified as the preferred supplier to carry out the work. The opportunity was advertised via open tender on pro-contract for a period of three weeks. Only one response was received from TUC Limited. The response has been evaluated by SMS plc (Enterprise Zone Utility Consultants) and the Council and is considered to provide value for money.

Contact: Neil Batt, Enterprise Zone Capital Programme Manager Email: Neil.Batt@herefordshire.gov.uk Tel: 01432 383694.

Publication date: 08/06/2021

Date of decision: 08/06/2021