Decision details
Pothole & Challenge Fund - Programme of works - Visala additional drainage works
Decision Maker: Acting Assistant Director for Highways and Transport
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
On 17 September 2020 the Director for Economy
and Place under the delegation from the Council of 6 August 2020
confirmed the addition of £7.674m pothole and challenge fund
works to he delivered through the public realm annual plan
2020/2021 as follows:
Carriageway Works
£ 2,604,000
Structures and Stability
£ 3,160, 000
Footways & Cycleway
£ 400,000
Countywide Drainage Improvements
£ 760,000
Signal, Roadmaking,
£ 750,000
Signs & Safety Barriers
Total
£ 7,674,000
That record of officer decision can be seen on the council’s
website by following the link below
http://councillors.herefordshire.gov.uk/ieDecisionDetails.aspx?ID=7176
£330,000 of the countywide drainage improvements elements was
to Visala
identified drainage works.
This Rood confirms the programme for that element of works as
follows:
C1094 Outside Weobley High School £50,000
C1120 The God Almighty, Litmarsh £40,000
C1125 C1129 to C1124, Marden £40,000
C1031 A4111 to Upper Spond £80,000
C1261 Railway Bridge to U71616, Dinedor £120,00
The programme detailed is derived from known Visala survey
data.
The programme may change slightly after full measurements are
taken, any changes will be accommodated through the CMT team change
control process.
Contact: John Manterfield, Commercial and Contract Manager Email: John.Manterfield@herefordshire.gov.uk.
Publication date: 30/11/2020
Date of decision: 30/11/2020
Accompanying Documents: