Decision details
Decision to agree a variation of design services for the Ross Enterprise Park project with Engie Regeneration Ltd
Decision Maker: Director of Economy and Place (Historic)
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Decision:
• To agree new design services for the
Ross Enterprise Park project with Engie Regeneration Ltd for
£64K in addition to the original 2018 new project request and
the previous £44K approval.
• To approve internal highways and planning fees in relation
to the above services at a cost up to £6000
Contact: Roger Allonby, Service Director Economy and Growth Email: Roger.Allonby@herefordshire.gov.uk Tel: 01432 260330.
Publication date: 12/11/2019
Date of decision: 05/11/2019
Accompanying Documents: