Approval of contingency budget to finance “change events” that will mitigate risks occurring in the Shell Store project
Decision Maker: Director of Economy and Place (Historic)
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Decision:
Approve the use of is £27,343.44 from
the Shell Store project contingency approved budget on repairs to
the concrete floor slab £25,639.56, and repairs to the steel
frame £1,703.88 specialist explosives testing, and
remediation and validation surveys and lead testing
Contact: Nick Webster, Economic development manager Email: nwebster@herefordshire.gov.uk Tel: 01432 260601.
Publication date: 12/11/2019