Decision details
Decision to fund £50,000 of Section 106 monies for “Sports” towards the creation of an off road skills area, enhancements to the learn to ride area, an additional toilet facility and enhancements to the cycle hub at Herefordshire Leisure Centre, Holm
Decision Maker: Service Director – Environment , Highways, & Waste
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
The Section 106 Contributions arise from one
Section 106 legal agreement:
Planning Reference GT / FIN Code Original Contribution S106
Allocation Expiry Date
P191770/O GT04 FIN2193 £79,117.00 £50,000.00
12/09/2032
TOTAL £50,000.00
The decision to fund £50,000.00 will not fully utilise the
Section 106 Contribution. The remaining contribution balance of
£29,117.00 will be appropriately commissioned and come
forward for delivery in due course.
The allocated project will support the creation of an off road
skills area aimed at young adults 14-24 year olds, enhancements to
the learn to ride area, an extra toilet and enhancements to the
cycle hub infrastructure to better support and further improve
disability access and the use of the facility. The additional
toilet facility will also support hockey and the particular issues
raised by Hereford Hockey club of accessing facilities.
The project contribution of £50,000.00 from Section 106
Sports contributions will be used as match funding of the
supplementary grant from Sports England of £50,000.00
received by the project. Indicative costs for the total match
funding is:
• 65k Off road Skills Area development
• £10k Enhancements to Learn to ride area
• £15k Cycle Hub infrastructure enhancements: extra
toilet, better disability access
• £10k Pathway reinstatement
The Cycle Project at Hereford Leisure Centre went out to tender in
March 2022. The process was agreed by the two main funding
providers Sport England and Herefordshire Council. The project
construction contract was subsequently awarded to OwenPel Limited
(based in Hereford) for a sum of £1,025,000. The project
commented on 27th November 2022 and is due for completion early in
August this year.
We are therefore satisfied that a sufficient tendering exercise has
been completed in accordance with Herefordshire Councils Contract
Procurement Rules (CPR).
Responsibility for monitoring the project and managing expenditure
within the total spend budget is to be with the S106 Programme
Manager.
Contact: Mark Averill, Service Director Environment and Highways Email: mark.averill@herefordshire.gov.uk Tel: 01432 260944.
Publication date: 23/03/2023
Date of decision: 21/03/2023