The 2018/19 Corporate Accommodation Capital
Budget included £90k to
carry out basic alteration works at Leominster Multi Agency Office.
During the design process additional requirements for joint
occupation of both the MAO/Locality team such as improving heating
and sound insulation were incorporated. Tenders have been received
and the lowest tender would result in an estimated final cost,
including contingency, of £180k. To overcome the short fall a
spend of not more than £90k from the underspend of the
2018/19 property estate enhancement works budget is required.
Contact: Chris Jenner, Assistant director for technical services Email: cjenner@herefordshire.gov.uk Tel: 01432 261941.