To approve the provision of technical advice by the Wye and Usk Foundation on phosphate reduction in the Lugg catchment

Published Related issues
TitleDate CreatedDue DateDecision MakersIssue Status
The construction and management of Integrated Wetlands as tertiary treatments for waste water treatment works to reduce phosphate levels within the River Lugg catchment area20/04/202010 August 2020Cabinet member Infrastructure and transportRecommendations Approved
To approve expenditure up to the value of £65,500 to award professional services contracts and to complete feasibility work to progress the Integrated Wetlands project17/02/202116 December 2020Director of Economy and Place (Historic)Recommendations Approved
Appointment of consultants to develop an Interim Phosphate Delivery Plan following the completion of a procurement process27/05/202114 October 2020Assistant Director for Regulatory, Environment and Waste Services (Historic)Recommendations Approved
Approve expenditure up to £148,000 for survey works and professional fees necessary to progress proposed integrated wetland sites18/06/202117 June 2021Assistant Director for Regulatory, Environment and Waste Services (Historic)Recommendations Approved
To approve expenditure up to £165,150 for the detailed design, planning and construction oversight for 3 wetland sites, and to enter into a contract with the Wye and Usk Foundation14/12/202114 December 2021Service Director – Environment , Highways, & WasteRecommendations Approved
Approval for the development of the phosphate credit framework by Ricardo-AEA Ltd for £22,73901/02/202227 January 2022Service Director – Environment , Highways, & WasteRecommendations Approved
To acquire land and associated access/easement rights to develop a phosphorous-reducing wetland09/02/202231 January 2022Service Director – Environment , Highways, & WasteRecommendations Approved
To approve expenditure up to £495,000 for construction of an integrated wetland scheme on land at Luston09/02/20221 February 2022Service Director – Environment , Highways, & WasteRecommendations Approved
To approve expenditure up to £495,000 for construction of an integrated wetland scheme on land at Luston and to enter into a contract with JN Bentley Ltd16/02/20221 February 2022Service Director – Environment , Highways, & WasteRecommendations Approved
To approve expenditure up to £75,000 for the design and construction of drainage apparatus at Luston waste water treatment works04/03/20224 March 2022Service Director – Environment , Highways, & WasteRecommendations Approved
Approval for the development of the phosphate credit framework by Ricardo-AEA Ltd for £22,73918/03/202227 January 2022Service Director – Environment , Highways, & WasteRecommendations Approved
Acquire land and associated access rights at Titley in order to develop a phosphorous-reducing wetland site01/04/202225 March 2022Service Director – Environment , Highways, & WasteRecommendations Approved