Issue details
S104 agreement and Deed of Grant of Easement for new foul drainage at the North Magazine, Hereford Enterprise Zone
Detailed technical discussions have taken
place between the EZ’s procured drainage engineers (One Ltd)
and DCWW to agree a suitable drainage design to serve the North
Magazine. Given the multiple potential connections, this needs to
be a public sewer owned by DCWW.
A Section 104 (sewerage adoption) agreement and Grant of Deed of
Easement is required with DCWW to enable them to adopt this
proposed new sewer on the North Magazine. These legal agreements
need to be in place before the installation can start.
Decision type: Non-key
Decision status: Recommendations Approved
Notice of proposed decision first published: 05/04/2021
Decision due: 5 April 2021 by Director of Economy and Place (Historic)
Contact: Neil Batt, Enterprise Zone Capital Programme Manager Email: Neil.Batt@herefordshire.gov.uk Tel: 01432 383694.
Decisions