Decision to deliver improvement works at Leominster MAO

Following the completion of works on site there are some additional items that have now been highlighted. The Localities Team require two more Paxton’s securing their area and the heating in the Children’s Centre needs to be upgraded as some of their radiators are now within the new meeting room leaving the main area low on heating and without radiator covers. A hot water boiler is also to be installed to replace the current kettle along with other minor works.

Decision type: Non-key

Decision status: Recommendations Approved

Notice of proposed decision first published: 07/01/2021

Decision due: 6 January 2021 by Director of Economy and Place (Historic)

Contact: Chris Jenner, Assistant director for technical services Email: cjenner@herefordshire.gov.uk Tel: 01432 261941.