Issue details
To fund capital works at Hereford leisure Pool
The leisure pool remains closed due to flood
damage. Insurance re-instatement works are well underway however to
ensure the leisure pool can be re-opened the following capital
works must be procured:-
Site area Regulatory works £
Plant room lighting 15,830
Electrical upgrade 169,802
Lightening protection 23,817
Fire alarm replacement 172,697
Plant room flat roof 14,736
Roof anti climb measures 8,358
Concrete repairs 77,000
Roof mounted pipework 22,000
Totals 504,239
The actual cost detail continues to be assessed and reviewed
however the above is a good indication of the expected costs
Decision type: Non-key
Decision status: Recommendations Approved
Notice of proposed decision first published: 26/10/2020
Decision due: 26 October 2020 by Director of Economy and Place (Historic)
Contact: Philip Huggett, Special projects officer Email: philip.huggett@herefordshire.gov.uk Tel: 01432 260018.
Decisions
- 26/10/2020 - To fund capital works at Hereford leisure Pool