Issue - decisions

Hereford City Centre Transport Package (HCCTP)

22/01/2021 - Hereford City Centre Transport Package (HCCTP)

That:

(a)       within the overall capital programme allocation of £40.651 million for the Hereford city centre transport package (HCCTP), a £1.377m  increase in budget for City Link Road Land Acquisition to £16.25m, and a £1.318m reduction in budget for the Transport Hub and Public Realm to £5.172m, be approved; and

(b)  the Director for Economy and Place in consultation with the Section 151 officer be authorised to take all operational decisions necessary to make the remaining City Link Road land acquisition payments.