Issue - decisions
Approval of contingency budget to finance “change events” that will mitigate risks occurring in the Shell Store project
14/08/2019 - Approval of contingency budget to finance “change events” that will mitigate risks occurring in the Shell Store project
Approve the use of £169,907 from the
Shell Store project contingency approved budget on the following
expenditure items which have been raised as “change
events” through the design implementation:
• £1,978 for appointment of BREEAM sustainability
champion
• £13,526 for asbestos removal to concrete slab;
• £20,504 for temporary utility supplies;
• £98,484 for ground works;
• £35,415 for groundwork design fees;