Decision details
Approval of the expenditure of up to £62,740 from the Capital maintenance Schools’ Budget for replacement windows works to St David’s Centre.
Decision Maker: Assistant Director Education, Development and Skills (Historic)
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
1. Award Balfour Beatty the contract to
complete the replacement windows works at St David’s Centre
up to the value of £57,749 to include a contingency value of
up to £7,880 from the contingency allocation. Responsibility
for managing and monitoring the project to be carried out by the
Capital Project Manager, within the spend budget.
2. To authorise the expenditure of up to the value of £4,990
from the professional fees allocation as set out in the Cabinet
Decision. Responsibility for managing and monitoring the project to
be carried out by the Capital Project Manager, within the spend
budget.
Contact: Ceri Morgan, Education Strategic Projects Email: ceri.morgan@herefordshire.gov.uk.
Publication date: 14/10/2020
Date of decision: 07/10/2020