Decision details

Approval of contingency budget to finance “change events” that will mitigate risks occurring in the Shell Store project

Decision Maker: Director of Economy and Place (Historic)

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

Approve the use of £169,907 from the Shell Store project contingency approved budget on the following expenditure items which have been raised as “change events” through the design implementation:

• £1,978 for appointment of BREEAM sustainability champion
• £13,526 for asbestos removal to concrete slab;
• £20,504 for temporary utility supplies;
• £98,484 for ground works;
• £35,415 for groundwork design fees;

Contact: Nick Webster, Economic development manager Email: nwebster@herefordshire.gov.uk Tel: 01432 260601.

Publication date: 14/08/2019

Date of decision: 14/08/2019