Decision details

Approval of the expenditure of up to £27,715 from the Capital Maintenance Schools’ Budget for emergency boiler replacement works to Bredenbury School

Decision Maker: Assistant Director Education, Development and Skills (Historic)

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

Agreement to:
1. Approve the expenditure of up to £27,515 from the contingency allocation for the boiler works at Bredenbury School. This includes £2,500 contingency. Responsibility for managing and monitoring the project to be carried out by the Capital Project Manager, within the spend budget.

2. To authorise the expenditure of up to the value of £200 for professional fees from the contingency allocation. Responsibility for managing and monitoring the project to be carried out by the Capital Project Manager, within the spend budget.

3. To add this emergency works scheme to the 2020/21 maintenance programme.

4. Bredenbury School are to self-deliver the boiler replacement works and have provided a tender report.

Contact: Ceri Morgan, Education Strategic Projects Email: ceri.morgan@herefordshire.gov.uk.

Publication date: 26/03/2021

Date of decision: 25/03/2021