Decision details
approve the expenditure of up to £5,470 from the Capital Maintenance Schools’ Budget for damp works to Wellington Primary
Decision Maker: Assistant Director Education, Development and Skills (Historic)
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
Award Balfour Beatty the contract to complete
the damp works to Wellington Primary School up to the value of
£4,630 to include a contingency value of £450 from the
contingency allocation.
Responsibility for managing and monitoring the project to be
carried out by the Capital Project Manager, within the spend
budget.
To authorise the expenditure of up to the value of £840 from
the professional fees allocation as set out in the Cabinet
Decision.
Responsibility for managing and monitoring the project to be
carried out by the Capital Project Manager, within the spend
budget.
Contact: Ceri Morgan, Education Strategic Projects Email: ceri.morgan@herefordshire.gov.uk.
Publication date: 14/10/2020
Date of decision: 07/10/2020