Decision details
Approval of contingency budget to finance “change events” that will mitigate risks occurring in the Shell Store project
Decision Maker: Director of Economy and Place (Historic)
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Decision:
Approve the use of £169,907 from the
Shell Store project contingency approved budget on the following
expenditure items which have been raised as “change
events” through the design implementation:
• £1,978 for appointment of BREEAM sustainability
champion
• £13,526 for asbestos removal to concrete slab;
• £20,504 for temporary utility supplies;
• £98,484 for ground works;
• £35,415 for groundwork design fees;
Contact: Nick Webster, Economic development manager Email: nwebster@herefordshire.gov.uk Tel: 01432 260601.
Publication date: 14/08/2019
Date of decision: 14/08/2019